For the seventh plant room update, we have another long list of changes and updates, most notably- we now have running hot water, the Asbestos removal preparation is complete and the fitting of the pool plant equipment has begun!
Next week we are hoping to see the completion of the Asbestos removal, and the restarting of the poolside's structural support work. Thanks for reading and see you next week! Dan | |
Also contained in the plant works is the planned under-pool structure support for the poolside floors. Poor ventilation and the resulting hot, humid air underneath the poolside has caused significant corrosion of the steel girders that support the concrete slabs upon which the floor tiles sit. These girders need to be replaced in order to ensure that the structural integrity of the poolside is maintained. This work will be carried out alongside the replacement of the heating and drainage pipework under the poolside as part of the new plant room installation. Undertaking this work alongside the plant room ensures the pool is closed only for the current six weeks and not again in the future for an undetermined length of time; causing yet more disruption for the club.
On behalf of all the club staff & The HRA Management Company; I would like to extend my thanks to everyone for the positive feedback we have received from members so far regarding this work. Whilst having the pool closed for this time is an unpleasant eventuality; I am grateful for the understanding and patience that has been expressed by you all and we hope to get the pool back up and running as soon as possible, and hopefully with no delays! I am aiming to update this page on a weekly basis with photos and information so you can all see how the work is progressing. Thanks & see you next week! Dan
|